Sanwo-Olu Explains Delay in Opebi-Odoiya Alaro Bridge Opening
Motorists in Lagos can expect a new commuting experience on the completed Opebi-Odoiya Alaro Bridge once its final architectural feature—a 25-metre steel monument—is fully installed, Governor Babajide Sanwo-Olu has revealed.
During an unscheduled visit to the bridge site on Sunday, Sanwo-Olu inspected the progress of Julius Berger’s installation of the landmark steel ornament, which has delayed the bridge’s official opening.
The Governor explained that although the monument was not part of the bridge’s original design, it was conceived during the late stages of construction to commemorate the site’s heritage as a cane market and to enhance the bridge’s aesthetics.
Sanwo-Olu called for patience from Lagosians, emphasising the importance of a safe and complete installation.
“Engineering designs are about innovation and uniqueness. This site will host about 300 tonnes of steel at 25 metres high, reflecting the historic craft of cane weaving. Three of the four steel hands are installed, with the final one set to begin. This is an extreme engineering process, and we must ensure safety before opening the bridge to traffic,” he said.
The Governor acknowledged the delay from the previously announced September opening, attributing it to the complexity of installing the monument. He praised the Ministry of Works and Infrastructure and the construction team for their accelerated efforts and urged them to further hasten the process.
“The work is at 80 per cent completion. Once the final steel hand is installed and other features added, the bridge will become an iconic Lagos infrastructure. If we have waited this long, we must ensure the result makes every Lagosian proud,” Sanwo-Olu said.
He assured that the bridge would be open to traffic for the Yuletide, adding that the new structure would not just improve commuting but also serve as a site for recreation, tourism, and heritage in Lagos.